There are two columns variance and progress in Time tracking Report, how to get the data for variance and progress? Is there any formula?

Answer

  • Original Estimate is initial estimated time.
  • Est. Time Remaining is current estimation in Estimate field. It is reduced when work is logged on an issue, and may be increased as well if there is more work needed.
  • Time Spent is sum of worklogs for an issue, during period. Note, there is Jira issue Timespent field also, which is overall value of time logged for an issue.
  • Estimate = Time Spent + Est. Time Remaining.
  • Variance = Original Estimate - Estimate.
  • Original Estimate Remaining = Original Estimate - Time Spent.
  • Progress is Timespent / ( Est. Time Remaining + Timespent), so it's 100% when Est. Time Remaining is 0.

All columns may present summed values, if Sum Sub-Tasks is on or Group By option is set.