- Original Estimate is initial estimated time.
- Est. Time Remaining is current estimation in Estimate field. It is reduced when work is logged on an issue, and may be increased as well if there is more work needed.
- Time Spent is sum of worklogs for an issue, during period. Note, there is Jira issue Timespent field also, which is overall value of time logged for an issue.
- Estimate = Time Spent + Est. Time Remaining.
- Variance is = Original Estimate - Estimate.
- Original Estimate Remaining = Original Estimate - Time Spent.
- Progress is Timespent / ( Estimated Est. Time Remaining + Timespent), so it's 100% when Estimated Est. Time Remaining is 0.